Lincoln County has upcoming openings for the Library Board (2), Planning and Zoning Commission (1 rural) and (1 within a municipality), Recreation Commission (2), Travel and Tourism Board (2) and Star Valley Community Complex Board (1). If you are interested in volunteering your time to serve, please send a letter, by April 30, 2025 to the Lincoln County Commissioners at the attention of Stephen P. Allen, MBA, Chief of Staff at stephen.allen@lincolncountywy.gov
PUBLISHED: April 22, 2025
Notice of Special Budget Work Session
Notice is hereby given that the Kemmerer City Council will hold a special budget work session. The special work session will begin at 4:00 p.m. Thursday, May 1, 2025, and at 4:00 p.m. on Friday, May 2, 2025, in the Kemmerer City Hall Council Chambers, 220 Wyoming Hwy 233, Kemmerer, WY.
PUBLISHED: April 22, 2025
PUBLIC NOTICE
Pursuant to the Wyoming Administrative Procedure Act and the Wyoming Public Service Commission’s (Commission) Rules and Regulations, notice is hereby given of the Application of Rocky Mountain Power (RMP or the Company) requesting authority to decrease rates, recover deferred Net Power Costs (NPC) under Tariff Schedule 95; and to decrease rates under Tariff Schedule 93, Renewable Energy Credits (RECs) and Sulfur Dioxide (S02) emission allowances, as more fully described below:
of supplying electric utility service to customers throughout its six -state service territory, including Wyoming under certificates of public convenience and necessity issued by the Commission. RMP is a public utility subject to the Commission’s jurisdiction. Wyo. Stat. §§ 37-1-1 01 (a)(vi)(C) and 37-2-112.
pursuant to two different rate schedules. The Company proposes to recover approximately $83.2 million of deferred NPC and under Tariff Schedule 95 its Energy Cost Adjustment Mechanism (ECAM) over a 12 month period. The Company also proposes to credit approximately $4.3 million to customers to reflect the sale ofRECs and S02 emission allowances under its Tariff Schedule 93 REC and S02 Revenue Adjustment Mechanism (RRA). The Company requests interim approval of the proposed rates effective for usage on and after July 1,2025, subject to further review.
Within each rate schedule, the percentage change to individual customers may be higher or lower than the average due to rate design, customer load factors, and usage characteristics. The combined effect of the 2025 RRA and ECAM in this Application represents an overall proposed rate decrease of approximately $46.9 million or 5.8 percent.
Residential Combined Proposed
Percentage Change (%)
Schedules 2, 19 (4.6)%
General Service
Schedule 25 (4.8)%
Scheduled 28, 29 (6.7)%
Large General Service
Schedule 33 (4.1)%
Schedule 46 (4.0)%
Schedule 48T (8.2)%
Irrigation
Schedule 40 (3.6)%
Lighting Schedules
Schedule 15 (3.8)%
Schedule 51 (2.5)%
Schedule 54 (6.8)%
Schedule 58 (8.8)%
Overall (5.8)%
Application at RMP’s Wyoming offices and at the Commission’s offices in Cheyenne, Wyoming, during regular business hours or online at https://dms.wyo.gov/extemal/publicusers.aspx (Enter Record No. 17791) or RMP’s website at www.pacificorp.com.
or request for a public hearing in this matter must file with the Commission in writing on or before May 16, 2025. Petitions shall set forth the grounds of the proposed intervention or request for hearing as well as the position and the interest of the petitioner in this proceeding.
for a disability, please contact the Commission at (307) 777-7427, or write to the Commission at 2515 Warren Avenue, Suite 300, Cheyenne, Wyoming 82002, to make arrangements. Communications impaired persons may also contact the Commission by accessing Wyoming Relay at 711. Please mention Docket No. 20000-682-EM-25 in your communications.
Dated: April 16, 2025
PUBLISHED: April 22, 20, 2025 23413
CALL FOR BIDS:
Canyon Elementary School Window Replacement
Lincoln County School District No. 1 (the Owner) is receiving lump sum sealed proposals for the Canyon Elementary School Window Replacement. The project scope includes but is not limited to all work necessary to complete the removal and replacement of exterior windows. Including but not limited to adjacent trims, flashings, finishes and other miscellaneous items required to complete work in full. This project is to be awarded under a single Contract.
First copies of the contract documents will be available after April 8th, 2025 and open to public inspection in the office of the Owner or Plan One/Architects, 4020 Dewar Drive, Suite A, Rock Springs, WY 82901. Paper plans and specifications will not be available, prime bidders must download plans utilizing www.questcdn.com. Quest Project Number: 9626292
A pre-bid conference will be held at the project site on April 29th, 2025 beginning at 3:30 p.m. Attendees shall meet at 1310 Antelope Street, Kemmerer, Wy 83101. The conference will be mandatory for all General Contractors wishing to have their bid considered for the work.
All proposals must be accompanied by a Bid Bond or Cashier’s Check in the amount of ten percent (10%) of the maximum amount of the proposal. The successful bidder shall provide a one hundred percent (100%) Performance and Payment Bond. The bidder is required to comply with all applicable local, state, and federal laws.
The Owner reserves the privilege of rejecting any or all proposals, or waiving any irregularities or formalities in any proposal in the bidding. Submit written proposals to: Lincoln County School District No. 1, ATTN: Kim Zuniga, 11 Adaville Drive, Diamondville, WY 83116 Sealed proposals shall be marked “Canyon Elementary School Window Replacement” and shall state the name of the company bidding on the outside of the envelope WYOMING DEPARTMENT OF TRANSPORTATION
CHEYENNE, WYOMING
NOTICE OF ACCEPTANCE OF AND FINAL SETTLEMENT FOR HIGHWAY WORK
Notice is hereby given that the Wyoming Department of Transportation has accepted as completed according to plans, specifications and rules governing the same work performed under that certain contract between the State of Wyoming and H-K Contractors, Inc., The Contractor, on Highway Project Number B243017 in Lincoln and Sublette Counties, consisting of chip seal and traffic control and the Contractor is entitled to final settlement therefore; that the Director of the Department of Transportation will cause said Contractor to be paid the full amount due him under said contract on May 26, 2025.
The date of the first publication of this Notice is April 15, 2025.
Pam Fredrick
Senior Budget Analyst
Budget Program
Wyoming Department of Transportation
PUBLISHED: April 15, 22, 29, 2025
. Proposals must be received by the 8th day of May, 2025 at 10:00 a.m. Proposals will not be accepted after this date and time. Proposals will be read aloud at that date and time.
Dated: April 8, 2025
Also as posted on the Quest Construction Data Network Site: Quest Project Number: 9626292
PUBLISHED: April 8, 15, 22, 2025